In summary, the scope of the project concerns the electrification and the installation of anti-noise soundproofing of the Kiato – Rododafni section of the New Double High Speed Railway Line of the Piraeus – Athens – Kiato – Patras railway network.

Project Contractor: K/X TERNA S.R.O. – MYTILINAEOS S.R.O. RHODODAPHNE)
Employer or Project Owner: ERGOSE SA.
Construction period: 30 months from the signing of the contract (06-07-2022)

ΚΑΤΑΣΤΑΣΗ

Under Construction

ΧΩΡΑ

Greece

ΚΑΤΗΓΟΡΙΑ

Infrastructure